CTRL Contract 350 Medway Crossing

  Client: Union Railways (South) Limited
 

Contractor:

Eurolink Joint Venture
  Value: £26m
  Date:

November 1999 - bridge 
completion in 2001

 
The Channel Tunnel High Speed Rail Link crosses the Medway estuary by a major viaduct, comprising two launched segmental post-tensioned concrete approach viaducts, totalling approximately 900m in length and an insitu concrete post-tensioned balanced cantilever main span section totalling 380m with a 190m maximum span.  The works were let to the Eurolink Joint Venture comprising Miller Civil Engineering, Beton et Monierbau and Dumez GTM.

Awards

  • British Construction Industry Awards 1995

  • The Concrete Society Awards 1995

Click here for other TGP Awards

 

 